Steel
4.87 t
9,734 lb
Linear feet
10,545
860 members
Trusses
39
24″ o.c., in-line
Sheathing
232
113 wall · 119 roof
Budgetary range
$111,000 – $180,000USD
$35–$56 / sf
Building kit$33,500 – $50,700
Doors & windows$7,000 – $12,000
Foundation$22,400 – $35,200
Erection labor$47,800 – $81,900
Budget only, not a quote. Planning rates, Oct 2026: regional material and labor factors and fixed exchange rates. Excludes land, site work, permits, engineering, utility connections, interior finishes and taxes.
Material takeoff
Counted from the framed model
| Category | Item | Qty | Unit | LF | lb | Notes |
|---|---|---|---|---|---|---|
| Wall framing | Stud — 362S162-33 | 105 | pcs | 1,576 | 1,460 | cut to length, longest 20′-10 1/16″ |
| King stud — 362S162-33 | 16 | pcs | 234 | 216 | cut to length, longest 18′-9 15/16″ | |
| Jack stud — 362S162-33 | 18 | pcs | 146 | 135 | cut to length, longest 11′-11 15/16″ | |
| Cripple stud — 362S162-33 | 19 | pcs | 106 | 98 | cut to length, longest 8′-0⅛″ | |
| Track — 362T125-33 | 28 | 20′ lengths | 550 | 401 | 24 runs, +7% waste | |
| Headers | Box header — 600S162-43 | 14 | pcs | 58 | 91 | cut to length, longest 4′-3¼″ |
| Box header — 1000S162-43 | 2 | pcs | 25 | 55 | cut to length, longest 12′-6½″ | |
| Bracing | X-strap — 4in flat strap-54 | 14 | 20′ lengths | 280 | 215 | 16 runs, +7% waste |
| Roof trusses | Truss chord — 362S162-43 | 117 | pcs | 3,285 | 3,967 | cut to length, longest 40′-0″ |
| Truss web — 250S162-33 | 507 | pcs | 2,580 | 2,049 | cut to length, longest 7′-3 3/16″ | |
| Roof | Hat channel — 150F125-33 hat | 95 | 20′ lengths | 1,883 | 1,163 | 22 runs, +7% waste |
| Sheathing | Wall sheathing ½″ exterior, 4×8 | 113 | sheets | 3,371 sf net of openings | ||
| Roof sheathing ⅝″, 4×8 | 119 | sheets | 3,542 sf incl. 1′ eaves | |||
| Cladding | 29 ga ribbed roof panel — Charcoal | 58 | pcs | cut 22′-3⅝″ | ||
| 29 ga ribbed wall panel, sidewalls — Ash Gray | 58 | pcs | cut 14′-1″ | |||
| 29 ga ribbed wall panel, endwalls — Ash Gray | 30 | pcs | cut to rake, 489 LF total | |||
| Ridge cap — Charcoal | 9 | 10′6″ sticks | 86 | 80 LF | ||
| Eave trim — Charcoal | 18 | 10′6″ sticks | 171 | 160 LF | ||
| Rake trim — Charcoal | 10 | 10′6″ sticks | 95 | 89 LF | ||
| Outside corner trim — Charcoal | 6 | 10′6″ sticks | 60 | 56 LF | ||
| Base trim — Charcoal | 26 | 10′6″ sticks | 257 | 240 LF | ||
| Opening trim — Charcoal | 16 | 10′6″ sticks | 159 | 149 LF | ||
| #12 × 1¼″ self-drill panel screw, color-matched | 5,196 | pcs | roof 80 / wall 60 per 100 sf | |||
| Fasteners | #10-16 × ¾″ hex washer head, self-drill | 8,860 | pcs | stud-to-track, headers, truss webs, purlins, straps | ||
| #8 × 1¼″ bugle head, self-drill | 9,930 | pcs | 6″ edge / 12″ field | |||
| Connections | Hold-down, strap bay ends | 16 | pcs | 8 braced bays | ||
| ½″ wedge anchor, bottom track @ 48″ o.c. | 64 | pcs | plus one each side of every door | |||
| Truss heel clip | 78 | pcs | 39 trusses @ 24″ o.c., in-line with studs |
First-cut framing and takeoff from prescriptive rules of thumb: member sizes, bracing and connections must be confirmed by a licensed engineer (AISI S240 / S400) before fabrication.